Update on planned closure of Bridgnorth and Hodnet highways depots
Shropshire Council has responded to concerns about the planned closure of its highways depot in Bridgnorth and Hodnet, by further explaining the reasons behind the proposals.
It was announced last month that the two depots are set to close as part of plans to improve the council’s highways maintenance service, with operations continuing at the three main depots in Whittington, Shrewsbury and Craven Arms.
No jobs will be lost, and modelling has demonstrated that there will be no detrimental impact on services to those areas currently covered by those depots. Indeed, it is typical of a council area of Shropshire’s size to be serviced by two to three highway depots.
Steve Charmley, Shropshire Council’s Cabinet member with responsibility for highways, said:
“Whilst the council has been investigating with our contractor Kier whether there is still a need to maintain five depots with current delivery models, there are many good and sensible reasons why we have had to fast-track temporarily moving operations from Bridgnorth and Hodnet. It’s important that we explain these, to reassure those residents and councillors that have raised concerns about these proposals and to reinforce that this is not a cut in services for those areas. Service levels will remain at the very least the same as the last year but with an expectation that there will be improvements.
“Having five depots in an area the size of Shropshire is something that may have been needed in years gone by, but this is no longer the case. The way that we work and the way we treat our roads has changed. There is no longer a one-size-fits-all approach to highways maintenance. We’re now using more specialist techniques, delivered through our supply chains, so we have far fewer council and contractor staff than we once did.
“The majority of work that takes place in the area that Bridgnorth and Hodnet serves is therefore not delivered by those depots but by others in the supply chain, and the staff in those depots therefore only undertake around 15% of the overall activity provided in their areas.
“Indeed, there haven’t been any Shropshire Council-employed staff in the Bridgnorth and Hodnet depots for about five years and, due to the relatively low numbers of contractor staff at those depots, during the pandemic Kier has at times struggled to have sufficient numbers to provide the number of gangs to undertake all works required – which has created a large backlog of outstanding works.
“In addition, a recent review of all five highways depots found that Bridgnorth and Hodnet are in a poor state of repair, and there are permit compliance concerns with the potential for the depots to be shut down with immediate effect by regulators if these issues aren’t addressed. However, to bring things up to standard would cost around £400,000 as Hodnet depot would require a complete rebuild and Bridgnorth would require the demolition of outbuildings and rebuilding of new facilities. This is money that could be far better spent on improving our roads.
“No decision has been taken to make these changes permanent, and they have been introduced purely to ensure continuing operational activity for those areas. However we will continue to review whether the limited monies available could be better spent on highways than maintaining the current number of depots and, if there is a business case to close depots in the future, this will be brought to Cabinet at the appropriate time.”
In the last month issues with the salt barn at the Bridgnorth depot have also been identified, which means salt will need to be moved to other salt barns in the county. Salt has corroded structural steel and it could be unsafe to operate a loading shovel out of there, and it’s unlikely that repairs will be able to be completed before the start of the winter services.
Street Scene services (fly tipping, grass cutting, hedge trimming) in Bridgnorth are operated out of the council’s Canternbrook building so will not be affected. The flood defence response (including provision of sandbags) can also be made available from those offices if needed, and out of hours operations are already provided from Craven Arms, Shrewsbury and Whittington.
The focusing of operations from three depots in Whittington, Shrewsbury and Craven Arms means that the council and Kier can be co-located so that there are better communications, oversight and consistency across the board, and will enable improvement in the quality of works and engagement with stakeholders. This approach has been demonstrated to be good practice across the country.
Rationalising teams also increases the operational resilience of the service during staff absences, as well improving the management of the health, safety and wellbeing of staff.
Each of the three remaining depots will be managed by an area manager from both Shropshire Council and Kier, supported by local technicians and supervisors.